eduleal
Member
Posts: 181
Joined: Mon Nov 18, 2013 6:07 pm

Sponsor licence application - Large company

Post by eduleal » Fri Sep 30, 2016 5:37 pm

Hi all,

Tier 2 visa holder here, in the process of changing employers.
Just wondering if anyone here has followed any sponsorship licence application recently?
Would anyone be able to advise how long it normally takes these days?

Official estimation I was given is between 8-10 weeks and it depends on whether there are pre-licence visits or not.

I have about 3.5 months before my current visa expires and have two conditional job offers to change (one from an employer with licence and one without a licence). Quite keen to change to the one without a licence - they have applied for their licence on the 12th of September. Just really hoping there is enough time for them to get it. They have both done the RLMT.

Also, this one is a very large company. Is that a positive or a negative in terms of getting a quicker outcome?
They really seem to be on top of it.

Any advice would be much appreciated!
Best,
Ed

User avatar
Frontier Mole
Respected Guru
Posts: 4437
Joined: Tue May 06, 2008 12:03 am
European Union

Re: Sponsor licence application timeline - Large company

Post by Frontier Mole » Fri Sep 30, 2016 7:42 pm

Size of business makes no difference in real terms. What can make a slight difference is the quality of the application secondary documents etc. Lease, accounts, bank statements etc.

If a larger firm uses one of the noted legal reps it usually means go more smoothly.

eduleal
Member
Posts: 181
Joined: Mon Nov 18, 2013 6:07 pm

Re: Sponsor licence application timeline - Large company

Post by eduleal » Sun Oct 02, 2016 6:54 pm

Frontier Mole wrote:Size of business makes no difference in real terms. What can make a slight difference is the quality of the application secondary documents etc. Lease, accounts, bank statements etc.

If a larger firm uses one of the noted legal reps it usually means go more smoothly.
Thanks for your reply.
Thoughts on current/recent processing times? I know it varies quite a bit, but on average?

iworker
Diamond Member
Posts: 2029
Joined: Thu Aug 09, 2012 2:11 pm
Location: Hampshire
Mood:
Pakistan

Re: Sponsor licence application timeline - Large company

Post by iworker » Mon Oct 03, 2016 9:13 am

2-3 months.

eduleal
Member
Posts: 181
Joined: Mon Nov 18, 2013 6:07 pm

Re: Sponsor licence application timeline - Large company

Post by eduleal » Mon Oct 03, 2016 10:24 am

Thanks, it seems there's time and they're really on top of it... I'll let you how long it takes.

iworker
Diamond Member
Posts: 2029
Joined: Thu Aug 09, 2012 2:11 pm
Location: Hampshire
Mood:
Pakistan

Re: Sponsor licence application timeline - Large company

Post by iworker » Mon Oct 03, 2016 11:32 am

The sponsor can give them a call, and if they do manage to speak to the right person (luckily), then they can send your visa copy showing that your visa is expiring soon, and then the process can be expedited.

eduleal
Member
Posts: 181
Joined: Mon Nov 18, 2013 6:07 pm

Re: Sponsor licence application timeline - Large company

Post by eduleal » Mon Oct 03, 2016 12:13 pm

Great to know. I think they would do that if it gets close. Hopefully it will be processed in the next 3 to 6 weeks, as it's been three weeks since all documents were sent.

Thanks for your help.

Mahir1108
Junior Member
Posts: 61
Joined: Mon Mar 14, 2016 4:38 pm

Re: Sponsor licence application timeline - Large company

Post by Mahir1108 » Mon Oct 03, 2016 1:59 pm

My sister is going to apply for Tier 2. Her company had applied for the Tier 2 License and the refusal letter came in 2 weeks since all the documents were sent by the company. The refusal was mainly due to a missing document which company forgot to send.

They have re-applied for the license again last week. Lets see when and what response they get this time.

Mahir1108
Junior Member
Posts: 61
Joined: Mon Mar 14, 2016 4:38 pm

Re: Sponsor licence application timeline - Large company

Post by Mahir1108 » Tue Oct 11, 2016 3:30 pm

The sponsor license has been approved and the letter came today so the time line is 3 weeks if you provide all the documents.

eduleal
Member
Posts: 181
Joined: Mon Nov 18, 2013 6:07 pm

Re: Sponsor licence application timeline - Large company

Post by eduleal » Wed Oct 12, 2016 10:50 am

Mahir1108 wrote:The sponsor license has been approved and the letter came today so the time line is 3 weeks if you provide all the documents.
Thanks for the update, Mahir1108!

It's actually been 4 weeks now since the company applied and no news (and no request for additional docs).
They called the Business helpdesk and were told they cannot discuss timelines before 8 weeks - so I guess we're on waiting mode until then.

By the 8 week mark it will be 2 months before my current visa expires, so I guess they'll be able to ask them to expedite it based on that.

eduleal
Member
Posts: 181
Joined: Mon Nov 18, 2013 6:07 pm

Re: Sponsor licence application timeline - Large company

Post by eduleal » Thu Oct 27, 2016 1:31 pm

6 weeks now since the company applied and no news.
Anyone else here followed a licence application recently and can share their timelines?

I guess if at this stage they haven't requested additional documents or scheduled a visit, that should be a good sign?

Or maybe that's just wishful thinking.

cherrypie
Junior Member
Posts: 59
Joined: Thu Jan 12, 2012 7:17 pm
Location: England
South Africa

Re: Sponsor licence application timeline - Large company

Post by cherrypie » Thu Oct 27, 2016 3:08 pm

Hi eduleal,

My company sent their licence application in on July 8th and licence was granted on July 28th.

Our circumstances are a bit different though. The company is very small and I already work for the company (almost 4 years) as a tier 1 visa holder. We also didn't need to do RLMt as my job is a shortage occupation. They applied for the licence solely to sponsor me so all my details were submitted with the licence application.

Hope this helps.

eduleal
Member
Posts: 181
Joined: Mon Nov 18, 2013 6:07 pm

Re: Sponsor licence application timeline - Large company

Post by eduleal » Mon Oct 31, 2016 10:50 am

Thanks, cherrypie, very useful to know.
My current company had a very similar experience when they applied. It was in 2013, though, when I think it was slightly faster too.

Let's see what happens to the new one!

eduleal
Member
Posts: 181
Joined: Mon Nov 18, 2013 6:07 pm

Re: Sponsor licence application timeline - Large company

Post by eduleal » Tue Nov 01, 2016 2:35 pm

Hi there,

Quick update just for the records, it seems the company got their licence approved this week as their name appeared on the sponsors register.

So exactly at the 7 weeks mark!

Cheers

cegun2003
Newly Registered
Posts: 5
Joined: Fri Oct 21, 2016 10:23 am

Re: Sponsor licence application timeline - Large company

Post by cegun2003 » Thu Nov 03, 2016 3:54 pm

Hi cherrypie,

You said your company is a small company. Do you mind sharing any information regarding the dcouments that were submitted i.e. audited account. Did your co0mpany submit UNAUDITED account for small companies?
My company is a small company. Normally small companies prepare abbreviated unaudited accounts and wondering if HO accepts this.

Thanks

noajthan
Moderator
Posts: 14911
Joined: Sat Oct 25, 2014 12:31 pm
Location: UK

Re: Sponsor licence application - Large company

Post by noajthan » Thu Nov 03, 2016 4:09 pm

This is not a timeline thread - no useful information about timelines found here; removed timeline from Subject.

Kindly note this is not a generic chat thread about anything under the sun remotely connected to sponsor and/or licence and/or company size.
All that is gold does not glitter; Not all those who wander are lost. E&OE.

cherrypie
Junior Member
Posts: 59
Joined: Thu Jan 12, 2012 7:17 pm
Location: England
South Africa

Re: Sponsor licence application timeline - Large company

Post by cherrypie » Fri Nov 04, 2016 8:22 am

cegun2003 wrote:Hi cherrypie,

You said your company is a small company. Do you mind sharing any information regarding the dcouments that were submitted i.e. audited account. Did your co0mpany submit UNAUDITED account for small companies?
My company is a small company. Normally small companies prepare abbreviated unaudited accounts and wondering if HO accepts this.

Thanks
Hi cegun2003,

I have no idea what documents were submitted on behalf of the company. HR took care of the application. Immigration lawyers were also consulted. I was only told that more documents were submitted than was required by the HO.

Even though we are now a small company we used to be a subsidiary/department of an international company and I think we still follow all the same procedures in place as when we were part of the larger company.

Sorry I couldn't be of any help.