ESC

Click the "allow" button if you want to receive important news and updates from immigrationboards.com


Immigrationboards.com: Immigration, work visa and work permit discussion board

Welcome to immigrationboards.com!

Login Register Do not show

Tier 1 (General) extension application processing timelines

Archived UK Tier 1 (General) points system forum. This route no longer exists.

Moderators: Casa, Amber, archigabe, batleykhan, ca.funke, ChetanOjha, EUsmileWEallsmile, JAJ, John, Obie, push, geriatrix, vinny, CR001, zimba, meself2, Administrator

Locked
TinaJohn
Newly Registered
Posts: 5
Joined: Tue Jan 05, 2010 6:09 pm

Post by TinaJohn » Fri Apr 12, 2013 12:15 pm

1. Current vignette: Tier 1 General Extension
2. Date of expiry of current leave: 21st April 2013
3. Number of dependent's applying at same time: 2
4. Date application posted: 23rd March 2013
5. Date application received at UKBA:
6. Date payment debited: 2nd April2013
7. Payment mode : Cheque
8. Acknowledgement letter received:
9. Biometric letter received:15th April 2013
10. Date of biometrics enrolment: 16th April 2013
11. Date of approval: 25thApril2013
12. Date of return of passport and other documents:13th may 2013
13. Date (new) leave to remain valid from: 25th April 2013
14. Date BRP received: 13th may 2013
Last edited by TinaJohn on Fri May 24, 2013 2:37 pm, edited 1 time in total.

rizash76
Newbie
Posts: 34
Joined: Mon Jul 26, 2010 3:01 am
Mood:
Pakistan

application app.

Post by rizash76 » Sun Apr 14, 2013 3:08 pm

Date submission. 15th of march 2013.
biomatric done:28th of march 2013.
biomatric card reciv. 12th apr 2013.
pass port reciv.13th of apr 2013.
it was a smooth transaction. unbelievable

khim
Newly Registered
Posts: 2
Joined: Mon Feb 02, 2009 2:23 pm

Post by khim » Mon Apr 15, 2013 11:20 am

1. Current vignette: Tier 1 General Extension
2. Date of expiry of current leave: 23rd March 2013
3. Number of dependent's applying at same time: 0
4. Date application posted: 5th March 2013
5. Date application received at UKBA: 6th March 2013
6. Date payment debited: 12 March 2013
7. Payment mode : Cheque
8. Acknowledgement letter received: 15 March 2013 (14 March 2013)
9. Biometric letter received: 29 March 2013 (dated 15th March, delivery to the wrong address and was found almost 2 weeks later)
10. Date of biometrics enrolment: 30 March 2013
11. Date of approval: Awaiting
12. Date of return of passport and other documents: Awaiting
13. Date (new) leave to remain valid from: Awaiting
14. Date BRP received: Awaiting

azhar_new2004
Newbie
Posts: 30
Joined: Wed Dec 16, 2009 10:30 am
United Kingdom

Tier 1 General Extension - Timescale

Post by azhar_new2004 » Mon Apr 15, 2013 11:58 am

1. Current vignette: Tier 1 General Extension
2. Date of expiry of current leave: 24th May 2013
3. Number of dependent's applying at same time: 0
4. Date application posted: 12th April 2013
5. Date application received at UKBA: 15th April 2013 (Royal Mail Website)
6. Date payment debited: 20th April 2013
7. Payment mode : Credit Card
8. Acknowledgement letter received: 24th April 2013 (Dated 19th April 2013)
9. Biometric letter received: 24th April 2013 (Dated 19th April 2013)
10. Date of biometrics enrolment: 4th May 2013
11. Date of approval: 16th May 2013
12. Date of return of passport and other documents: 17th May 2013
13. Date (new) leave to remain valid from: 16th May 2013 till 16th May 2016
14. Date BRP received: 31st May 2013
Last edited by azhar_new2004 on Fri May 31, 2013 1:48 pm, edited 5 times in total.

ccson
Newly Registered
Posts: 1
Joined: Tue Apr 16, 2013 1:24 pm
Location: London

Crazy fast!

Post by ccson » Tue Apr 16, 2013 1:29 pm

UKBA has been really smooth this time around, first ever!

Details:
1. Current vignette: Tier 1 (General) extension
2. Date of expiry of current leave: 13 April 2013
3. Number of dependants applying at same time: 0
4. Date application posted: 15 March 2013
5. Date application received at UKBA: 18 March 2013
6. Date payment debited: 18 March 2013
7. Payment mode : Postal orders
8. Acknowledgement letter received: 20 March 2013
9. Biometric letter received: 25 March 2013
10. Date of biometrics enrolment: 26 March 2013
11. Date of approval: 6 April 2013
12. Date of return of passport and other documents: 9 April 2013
13. Date (new) leave to remain valid from: 6 April 2013
14. Date BRP received: 16 April 2013

krishna6693
Member
Posts: 185
Joined: Mon Jun 29, 2009 6:21 am

Fastest ever approval for me from UKBA

Post by krishna6693 » Wed Apr 17, 2013 11:38 pm

1. Current visa: Tier 1 General
2. Date of expiry of current leave: 16 Apr, 2013
3. Number of dependants applying at same time: 2
4. Date application posted: 20 March, 2013
5. Date application received at UKBA: 21 March, 2013
6. Date payment debited: 22 March, 2013
7. Payment mode : Debit Card
8. Acknowledgement letter received: 25 March, 2013
9. Biometric letter received: 28 March, 2013
10. Date of biometrics enrolment: 02 Apr, 2013
11. Date of approval: 11 Apr, 2013
12. Date of return of passport and other documents: 13 Apr, 2013
13. Date (new) leave to remain valid from: 11 Apr, 2013
14. Date BRP received: 15 Apr, 2013

samira_uk
BANNED
Posts: 419
Joined: Thu Aug 05, 2010 4:05 pm

Re: Fastest ever approval for me from UKBA

Post by samira_uk » Thu Apr 18, 2013 9:12 am

krishna6693 wrote:1. Current visa: Tier 1 General
2. Date of expiry of current leave: 16 Apr, 2013
3. Number of dependants applying at same time: 2
4. Date application posted: 20 March, 2013
5. Date application received at UKBA: 21 March, 2013
6. Date payment debited: 22 March, 2013
7. Payment mode : Debit Card
8. Acknowledgement letter received: 25 March, 2013
9. Biometric letter received: 28 March, 2013
10. Date of biometrics enrolment: 02 Apr, 2013
11. Date of approval: 11 Apr, 2013
12. Date of return of passport and other documents: 13 Apr, 2013
13. Date (new) leave to remain valid from: 11 Apr, 2013
14. Date BRP received: 15 Apr, 2013
It is really fast!! UKBA reverts to good old days?

muditmalhotra
Member of Standing
Posts: 334
Joined: Tue Mar 09, 2010 9:19 pm

Post by muditmalhotra » Thu Apr 18, 2013 11:24 am

muditmalhotra wrote:1. Current vignette: Tier 1 (G)
2. Date of expiry of current leave: 20 April 2013
3. Number of dependants applying at same time: 1
4. Date application posted: 26th March
5. Date application received at UKBA: 27th March (Royal Mail website)
6. Date payment debited: 28th March, money went out on 2nd April (Easter)
7. Payment mode : Debit card
8. Acknowledgement letter received: o4 April dated 27th March
9. Biometric letter received: 5th April (Dated 2nd April)
10. Date of biometric enrollment: 8th April
11. Date of approval: 16 April
12. Date of return of passport and other documents: 17 April
13. Date (new) leave to remain valid from: 16 April 2013
14. Date BRP received: 18 April 2013


20 Days to approval !

krishna6693
Member
Posts: 185
Joined: Mon Jun 29, 2009 6:21 am

Re: Fastest ever approval for me from UKBA

Post by krishna6693 » Thu Apr 18, 2013 11:45 pm

Probably UKBA is prepared to expect lots of applications around 1st to 4th Apr nd clearing all prior applications ASAP.

digitalrev
Junior Member
Posts: 72
Joined: Mon Dec 06, 2010 10:07 am

Post by digitalrev » Fri Apr 19, 2013 3:48 am

1. Current vignette: Tier 1 General Extension
2. Date of expiry of current leave: 12 march 2013
3. Number of dependent's applying at same time: 0
4. Date application posted: 11 march 2013
5. Date application received at UKBA: 11 march 2013 (Royal Mail Website)
6. Date payment debited: Processed
7. Payment mode : Postal Order
8. Acknowledgement letter received: 15 March
9. Biometric letter received: 18 March
10. Date of biometrics enrolment: 22 March
11. Date of approval: 11 April
12. Date of return of passport and other documents: 12 April
13. Date (new) leave to remain valid from: 11 April
14. Date BRP received: 16 April

narendra_ydk
Newly Registered
Posts: 22
Joined: Tue Apr 19, 2011 1:10 pm

Post by narendra_ydk » Fri Apr 19, 2013 11:39 am

1. Current vignette : Tier 1 (G) first extension
2. Date of PEO Appointment : 19-Mar-2013
3. Number of dependents: 2
4. Employment: Employed (Limited Company Director / Salary + Divid)
5. Date of expiry of current leave (visa) : 01-Jun-2013
6. Date of expiry of the new visa : 19-March-2015
7. Payment mode : Credit Card (HSBC Credit Card and Debhenams)
8. Name of PEO Applied : Birmingham
9: Approval letter: Given on the same day
10. Dependents BRP Received on: 23-03-2013
11. My BRP received on 19-04-2013

Please notice the dates. I received my BRP after a month which my dependents got.
1. After 10 working days I sent a an email to BRPDelivery@homeoffice.gsi.gov.uk then they issued my BRP card but with incorrect visa dates.
2. Then I sent back my BRP card with covering letter to BRPError@homeoffice.gsi.gov.uk on 10-April-2013 and
3. Finally 19-04-2013 (today) I received my BRP with correct dates

k_tier1
Junior Member
Posts: 51
Joined: Tue Apr 09, 2013 8:40 pm

Tier 1 (General) extension application processing timelines

Post by k_tier1 » Fri Apr 19, 2013 1:51 pm

1. Current vignette: Tier 1 (General) Extension
2. Date of expiry of current leave: April 2013
3. Number of dependent's applying at same time: 0
4. Date application posted: 5 April 2013
5. Date application received at UKBA: 8 April 2013
6. Date payment debited: 16 April 2013
7. Payment mode : VISA Debit Card
8. Acknowledgement letter received: 22 April 2013
9. Bio metrics letter received: 22 April 2013
10. Date of bio metrics enrolment: 24 April 2013
11. Date of return of passport and other documents: 03 May 2013
12. Date (new) leave to remain valid from: 01 May 2013
13. Date BRP received: 03 May 2013
Last edited by k_tier1 on Thu May 09, 2013 9:24 pm, edited 5 times in total.

shiva_ts
Newly Registered
Posts: 3
Joined: Wed Apr 02, 2008 10:10 am

Re: Tier 1 (General) extension application processing timeli

Post by shiva_ts » Sat Apr 20, 2013 7:47 am

1. Current vignette: Tier 1 (General) Extension
2. Date of expiry of current leave: oct 2013
3. Number of dependent's applying at same time: 1
4. Date application posted: 4 April 2013
5. Date application received at UKBA: 5 April 2013
6. Date payment debited: 16 April 2013
7. Payment mode :Debit Card
8. Acknowledgement letter received: 19 apr 2013
9. Bio metrics letter received: 19 apr 2013
10. Date of bio metrics enrolment: -
11. Date of approval: -
12. Date of return of passport and other documents: -
13. Date (new) leave to remain valid from: -
14. Date BRP received: -[/quote]

veerug
Newly Registered
Posts: 8
Joined: Wed Aug 04, 2010 3:26 pm

Tier 1 (General) extension application processing timelines

Post by veerug » Mon Apr 22, 2013 4:31 pm

1. Current vignette: Tier 1 (General) Extension
2. Date of expiry of current leave: 08th July 2013
3. Number of dependants applying at same time: 2
4. Date application posted: 27 March 2013
5. Date application received at UKBA: 28 March 2013
6. Date payment debited: 03rd April 2013
7. Payment mode : Debit Card
8. Acknowledgement letter received: 08th April 2013
9. Biometric letter received: 06 April 2013
10. Date of biometrics enrolment: 12 April 2013
11. Date of approval: 09 may 2013
12. Date of return of passport and other documents: 12 May 2013
13. Date (new) leave to remain valid from: 09 May 2015
14. Date BRP received: 12 may 2013
Last edited by veerug on Wed May 22, 2013 1:44 pm, edited 1 time in total.

tahir52
Newly Registered
Posts: 1
Joined: Tue Apr 23, 2013 7:23 pm

Post by tahir52 » Tue Apr 23, 2013 7:37 pm

1. Current vignette: Tier 1 (General) Extension
2. Date of expiry of current leave: 13 Mar 2013
3. Number of dependants applying at same time: 1
4. Date application posted: 27 March 2013
5. Date application received at UKBA: 28 March 2013
6. Date payment debited: 02nd April 2013
7. Payment mode : Debit Card
8. Acknowledgement letter received: 08th April 2013
9. Biometric letter received: 12 April 2013
10. Date of biometrics enrolment: 12 April 2013
11. Date of approval: 18 April 2013
12. Date of return of passport and other documents: Waiting
13. Date (new) leave to remain valid from: 18 April 2013
14. Date BRP received: 23rd April 2013

khim
Newly Registered
Posts: 2
Joined: Mon Feb 02, 2009 2:23 pm

Post by khim » Wed Apr 24, 2013 7:09 pm

1. Current vignette: Tier 1 General Extension
2. Date of expiry of current leave: 23rd March 2013
3. Number of dependent's applying at same time: 0
4. Date application posted: 5th March 2013
5. Date application received at UKBA: 6th March 2013
6. Date payment debited: 12 March 2013
7. Payment mode : Cheque
8. Acknowledgement letter received: 15 March 2013 (14 March 2013)
9. Biometric letter received: 29 March 2013 (dated 15th March, delivery to the wrong address and was found almost 2 weeks later)
10. Date of biometrics enrolment: 30 March 2013
11. Date of approval: 22 April 2015
12. Date of return of passport and other documents: 24 April 2013
13. Date (new) leave to remain valid from: 22 April 2015
14. Date BRP received:24 April 2013

anandpathak
Member
Posts: 125
Joined: Sat Dec 12, 2009 5:46 pm
Location: London , UK
Contact:

Post by anandpathak » Mon Apr 29, 2013 9:37 am

anandpathak wrote:1. Current vignette: Tier 1 General Extension ( second extension)
2. Date of expiry of current leave: 28th Nov 2014 ( second extension required due to late entry by 6 months)
3. Number of dependent's applying at same time: 3
4. Date application posted: 03 April 2013
5. Date application received at UKBA: 04 April 2013
6. Date payment debited: 09 April 2013
7. Payment mode : HSBC MAster Credit Card
8. Acknowledgement letter received: None
9. Biometric letter received: 11 April 2013
10. Date of biometrics enrolment: 16th April 2013
11. Date of approval: Awaiting : 24th April 2013
12. Date of return of passport and other documents: Awaiting
13. Date (new) leave to remain valid from: Awaiting
14. Date BRP received: Awaiting
: 26th April 2013 (WRONG VISA VALID UNTIL DATE) - Preparing for correction Apeal now.

I folks I got my BRP and waiting for ymy passport now. The decision tooljust 22 days for me ( 8 days after biometric) but UKBA messed up the Validity dates . My iitial Visa was for 2 years as per the rules prevelant after 6th April 2010 and My Extensions should be of 3 years ( My first extension was indeed for 3 years) . This second extension have only been of 2 years thus I am falling short of ILR now by 5 months.
I am due for ILR in Oct 2015 and was expecting this new Visa valid till April 2016. I wonder why UKBA deprived me of this small happiness of getting CORRECT Visa in 22 days :(
Any personal experience of a similar situation , pls guide.
Cheers
Anand

maaan143
Newbie
Posts: 49
Joined: Mon Jun 28, 2010 8:29 pm
Location: London

Re: Tier 1 (General) extension application processing timeli

Post by maaan143 » Wed May 01, 2013 12:31 am

1. Current vignette: tier1 general
2. Date of expiry of current leave:10 april 2013
3. Number of dependants applying at same time:1
4. Date application posted:14-3-2013
5. Date application received at UKBA: 18-3-2013
6. Date payment debited: 22-3-2013
7. Payment mode : checque
8. Acknowledgement letter received: 30-3-2013
9. Biometric letter received: 12-4-2013
10. Date of biometrics enrolment: 12-4-2013
11. Date of approval:25-4-2013
12. Date of return of passport and other documents: awaiting
13. Date (new) leave to remain valid from:25-4-2013
14. Date BRP received: 30-4-2013

Note. had one invoice query, visa stumped soon after they recvd confirmation.
Last edited by maaan143 on Thu May 02, 2013 5:44 pm, edited 1 time in total.

srikiran14
Newly Registered
Posts: 1
Joined: Wed May 01, 2013 9:37 am

Post by srikiran14 » Wed May 01, 2013 9:41 am

1. Current vignette: Tier 1 General Extension
2. Date of expiry of current leave: 03rd May 2013
3. Number of dependent's applying at same time: 0
4. Date application posted: 30th April 2013
5. Date application received at UKBA: 01 May 2013
6. Date payment debited: 03 May 2013
7. Payment mode : Visa Debit
8. Acknowledgement letter received: 03 May 2013
9. Biometric letter received: 03 May 2013
10. Date of biometrics enrolment: 08 May 2013
11. Date of approval: 17 May 2013
12. Date of return of passport and other documents: Awaiting
13. Date (new) leave to remain valid from: 17 May 2013
14. Date BRP received: 20 May 2013

Thanks for all the updates !! and hope rest of you get yours sorted soon.
Last edited by srikiran14 on Tue May 21, 2013 4:37 pm, edited 3 times in total.

syed07
Newly Registered
Posts: 18
Joined: Wed Jan 30, 2013 8:12 am

tier1 general extension app processing timelines

Post by syed07 » Wed May 01, 2013 3:48 pm

1. Current visa : Tier 1 (General)
2. Date of expiry of current leave (visa): May 18, 2013
3. Date application posted: April 2, 2013
4. Date payment debited: april 8 , 2013
5. Payment mode: Bank Account Debit Card
6. Acknowledgement received: 13/04/2013
7. Biometric letter received :12/03/2013, enrolled 12/04 at Post Office
8. Date extension leave to remain valid from: 29/04/2013
9. Date passport received: 01/05/2013.
10. Date biometric card received: 01/05/2013
11. Numbers of dependant applied at the same time: 3

Thanks all of the members of this forum sharing their experiances and answers the required questions.

All the best to other applicant!

drdheer
Junior Member
Posts: 65
Joined: Sat Mar 20, 2010 8:34 am
United Kingdom

Post by drdheer » Wed May 01, 2013 7:27 pm

1. Current vignette: Tier 1 - General
2. Date of expiry of current leave: 21st April 2013
3. Number of dependants applying at same time: 2
4. Date application posted: 30th March 2013
5. Date application received at UKBA: 2nd April 2013
6. Date payment debited:
7. Payment mode : Bankers Draft
8. Acknowledgement letter received: 19th April
9. Biometric letter received: 19th April 2013
10. Date of biometrics enrolment: 22nd April 2013
11. Date of approval: 29th April 2013
12. Date of return of passport and other documents: 3rd May 2013
13. Date (new) leave to remain valid from: 29th April 2013
14. Date BRP received: 1st May 2013
Last edited by drdheer on Sat May 04, 2013 8:26 am, edited 1 time in total.

pshayer
Newbie
Posts: 38
Joined: Sun Jan 27, 2013 4:16 pm
India

Processing Time

Post by pshayer » Fri May 03, 2013 4:48 pm

1. Current vignette: Tier 1 - General
2. Date of expiry of current leave: 16th May 2013
3. Number of dependants applying at same time: 1
4. Date application posted: 5th April 2013
5. Date application received at UKBA: 8th April 2013
6. Date payment debited: 17th April 2013
7. Payment mode : Visa Card
8. Acknowledgement letter received: 20th April
9. Biometric letter received: 19th April 2013
10. Date of biometrics enrolment: 23nd April 2013
11. Date of approval: 30th April 2013
12. Date of return of passport and other documents: Awaited
13. Date (new) leave to remain valid from: 30th April 2013
14. Date (new) leave to remain valid Until: 30th April 2016
15. Date BRP received: 3rd May 2013

I am bit concerned about my wife's visa, her previous visa type was "TIER 1 (GENERAL) PARTNER * *****" and after extension the new one says "PBS DEPENDANT". I don't know if there is any difference!

drdheer
Junior Member
Posts: 65
Joined: Sat Mar 20, 2010 8:34 am
United Kingdom

Post by drdheer » Sat May 04, 2013 8:27 am

This is one and a same thing. Do not worry! Same is the case with my wife as well.

pshayer
Newbie
Posts: 38
Joined: Sun Jan 27, 2013 4:16 pm
India

Post by pshayer » Mon May 06, 2013 3:03 pm

drdheer wrote:This is one and a same thing. Do not worry! Same is the case with my wife as well.
Thanks for clarifying @drdheer

kolaxy
Junior Member
Posts: 74
Joined: Wed Jun 24, 2009 1:28 am
Location: somewhere...
Contact:

Post by kolaxy » Mon May 13, 2013 10:14 am

1. Current vignette: Tier 1 - General
2. Date of expiry of current leave: 13th July 2013
3. Number of dependants applying at same time: 1
4. Date application posted: 27th March 2013
5. Date application received at UKBA: 28th March 2013
6. Date payment debited: 3rd April 2013
7. Payment mode : Debit card
8. Acknowledgement letter received: 8th April
9. Biometric letter received: 5th April 2013
10. Date of biometrics enrolment: 5th April 2013
11. Date of approval: 9th May 2013
12. Date of return of passport and other documents: 11th May 2013
13. Date (new) leave to remain valid from: 9th May 2013
14. Date BRP received: 13th May 2013

The last 45days has been the longest of my life. Thanks everyone for your wonderful contributions and advice on this forum. My advice for everyone expecting his/her visa is to have enough patience as the ball is no more in our court. We can only pray. I believe 99.99% of us will get our visa approved. Wish you all the best of luck.


***Unto the Lord be ALL the glory, great things He has done***